BELL HELICOPTER TEXTRON, INC. Pic 1 | Pic 2 | Pic 3
BUILDING 26 CUP and DATA CENTER UPGRADES

Upgrade existing Central Plant to add additional load of chilled water for the entire building and more importantly the Data Center. The Data Center required uninterrupted service while maintaining building cooling.

Installed rental chillers, generators, and temporary 10 chilled water piping to feed the building and data center while maintaining uninterrupted service to both. Piping was installed through an occupied building and into the central plant where tie-ins were made to the existing system. Once these tie-ins were made the entire central plant equipment and piping were demoed and replaced with new equipment and piping.